For your convenience we have provided the timeline of our project. Please note this is an approximation. For any changes we will not be accountable (our contractors will be though!). However we do promise to update it every now and then.
Status: Completed. Floor: Basement.
Excavation for basement was started on 26-Febuary and completed on 08-March.
Status: Completed. Floor: Basement.
RCC foundation works for basement were started on 14-March and completed on 25-March.
Status: Completed. Floor: Basement.
Work on Down Slab Retaining Wall for basement was started on 18-March and completed on 08-April.
Status: Completed. Floor: Basement.
Work on Down area filling and pcc for basement was started on 30-March and completed on 05-April.
Status: Completed. Floor: Basement.
Work on R.C.C. Retaining wall (Upper Area) was started on 05-April and completed on 15-April.
Status: Completed. Floor: Basement.
Work on Down Slab for Basement was started on 05-April and completed on 12-April.
Status: Completed. Floor: Basement.
Work on PCC Filling (Under Floor) was started on 12-April and completed on 20-April.
Status: Completed. Floor: Basement.
Work on Upper Slab for Basement was started on 16-April and completed on 25-April.
With traditional architecture, state-of-art facilities and cardinal location, 9-ARCHES doesn't need to advertise for bookings. But we care about you and don't want your BRAND to miss out on 'once in a lifetime' oppurtunity (yeah right!). For booking enquiries, you can contact us directly or contact our representatives (Manifest Group). For an immediate and detailed attention, we prefer you contact our represtatives (we like pretending to be busy!) You can also visit our site and dig in with our contractors.